Every charger on the national network has to move to a new operator, and the owners’ deadline is 31 December 2026. Argyll finds an operator to take yours on and, where a unit is too old to move, supports the grant application for its replacement.

What the move means

ChargePlace Scotland is the public charging network Transport Scotland set up. It is winding down, and every charger on it has to move to a new operator: the company whose system takes payment and shows the charger on a public map. Arranging the move is the owner’s job, and the owners’ deadline is 31 December 2026, with staged deadlines through the year.

The move takes up to about three months once the units are confirmed and an operator appointed, and longer at remote sites. A host who has not appointed an operator by the end of September has little room to spare.

If nothing is done

When the old system ends, a charger with no new operator keeps giving out electricity, with nobody paying for it but the owner. Energy Saving Trust calls this free vend.

Units too old to move

The operators taking on ChargePlace Scotland chargers need them to run OCPP 1.6 or later, the protocol a charger uses to talk to its operator. A unit on OCPP 1.5 cannot move at all: it has to be replaced, retired, or left giving electricity away.

At a glance

Owners’ deadline
31 December 2026
Lead time
About three months
If nothing is done
Free vend, paid for by the owner
Cannot move
Units on OCPP 1.5
Replacement grant
100 per cent, up to a cap per unit
Who applies
The owner, with a committed operator

The Transition Fund

The ChargePlace Scotland Transition Fund, run by Energy Saving Trust for Transport Scotland, pays in full for a like-for-like replacement, up to a cap per unit: from £15,000 for a charger up to 22 kW to £60,000 for a rapid charger of 125 to 350 kW.

It is for public ChargePlace Scotland units that are at least five years old or on OCPP 1.5, in rural areas (urban rural classes 5 to 8) or where there are three or fewer public chargers within five miles, that were not funded under the Contactless Compliance Grant, and whose owner had not already signed with a new operator before 13 July 2026.

  • The owner applies. Applications made by anyone else are turned down.
  • An operator committed to adopting the new unit is a condition of applying.
  • One application covers every unit at a business address.
  • Offers are accepted within 14 days, and by 15 December 2026 at the latest.
  • The old unit comes off ChargePlace Scotland by 31 December 2026, and the works are complete by 15 March 2027.
  • The grant is paid on a claim once the new unit is live on the operator’s public map, and the unit stays public and working for five years.

Transport Scotland identified the eligible units, and Energy Saving Trust says it has contacted every eligible owner.

The process

How Argyll helps

Under a letter of authority you sign. Argyll’s fee is paid by the operator, not by you.

  1. You sign a letter of authority

    One page, for the move. It lets Argyll look into your chargers and speak to operators for you. Energy Saving Trust will only discuss your application with us once you have told them in writing, so the letter comes with the email to send.

  2. We check your chargers

    Their age, OCPP version and place decide whether each can move as it is or needs replacing, and whether the Transition Fund applies.

  3. You receive written proposals

    From operators prepared to take the site on. Some fund and run the charger and share the income, some lease the space, some supply the system while you keep the charger. Their terms are in writing before you sign anything.

  4. You apply, with an operator committed

    Where a unit needs replacing, the application is yours, made with the operator’s commitment in hand. We prepare it with you.

  5. The charger moves

    The operator and ChargePlace Scotland test the unit on its new system and switch it over, before 31 December 2026.

Rural and Island Infrastructure Fund

More chargers at the same time

The Transition Fund replaces a charger; the Rural and Island Infrastructure Fund pays only for new ones, never to replace, repair or upgrade a charger already there. So a rural or island host moving off ChargePlace Scotland can add more chargers under it at the same time, with 75 to 100 per cent of the eligible cost covered, up to a cap per charger.